ADPC Bi-Weekly Update #12: 04 April 2025
Focus Last 2 Weeks
Work Package 1 (RPCs)
- Completed the matchmaking process and awareness sprint to announce whitelisted providers.
- Providers still going through KYB and signing of Head Agreements with the Arbitrum Foundation.
- Onboarded Ankr (final provider); they did not previously respond to the whitelisting but got back recently.
Work Package 1 (Events)
- Materials to leave the DAO with post ADPC Phase II have been published on the forum.
Work Package 2 (Subsidy Fund)
- This work package has been completed, with only some back and forth between AF, projects, and providers.
Work Package 3 (OpEx Budget)
- Published the proposal on the forum (titled “Service Provider Utilisation Framework”).
Work Package 4 (Reporting & Management)
- Maintained constant updates and communications on the forum, TG chats, and X (Twitter).
- Paid Jess pending invoices.
Focus Next 2 Weeks
Work Package 1 (RPCs)
- This work package is now complete; management of back and forth between projects, providers, and AF where needed will take place.
Work Package 1 (Events)
- This work package is now complete.
Work Package 2 (Subsidy Fund)
- Continue management of back and forth between projects, providers, and AF where needed. Otherwise, this work package is now complete.
Work Package 3 (OpEx Budget)
- Incorporate feedback from discussion on the proposal. Otherwise, this work package is now complete.
Work Package 4 (Reporting & Management)
- Finalise any operational items and wrap-up of ADPC Phase II.
- Complete final outcome post / report for Phase II.